Table of Contents Table of Contents
Previous Page  10 / 20 Next Page
Information
Show Menu
Previous Page 10 / 20 Next Page
Page Background

Concrete Pavement Progress

www.acpa.org

12

J F K A I R P O R T

» continued from page 10

Working alongside operating taxiways also pre-

sented challenges with equipment operating at

the edge of the safety area, says Amoia. “We did

obtain some FAA concessions that allowed some

short bursts of closures during the day when the

work could not be done at night.”

Because speed of completion was critical, a select

list of contractors who might bid on the project

were invited to a mandatory workshop when

the project design was 70 percent complete, says

Zummo. “This gave them time to ask questions,

offer input and help us address potential issues

before construction began,” he says. “We also

worked closely with the FAA during the plan-

ning and design phase to be sure we were able to

propose new approaches and obtain approval.”

As with all projects, there were two lessons

learned with 4L-22R that Zummo and his team

will keep in mind for the next project. “We did

not account for the length of the paving train

when staging the work, and we did not allow

enough time to identify and verify electrical

infrastructure—a critical task because we were

moving electrical and lighting systems.” He adds,

“Even with extra time required for FAA activities

and electrical infrastructure, the runway was

put into service a week earlier than planned.”