Table of Contents Table of Contents
Previous Page  8 / 20 Next Page
Information
Show Menu
Previous Page 8 / 20 Next Page
Page Background

Concrete Pavement Progress

www.acpa.org

10

J F K A I R P O R T

The pavement portion of the $282million project

included:

• Constructing 728 feet of runway pavement

on the north side of the runway tomaintain

departure length

• Widening the runway from 150 feet to 200

feet to comply with the needs of Group

VI aircraft

• Rehabilitating the runway using concrete

to replace existing asphalt

• Constructing high-speed taxiways

• Constructing new taxiway exits leading to

the Central Terminal Area, new taxiway

access points to the north end of the runway,

and other taxiway modifications

“The concrete specification and mix proportions

used to construct runway 4L-22R were the result

of years of lessons learned and testing in the Port

Authority concrete laboratory on concrete used to

construct aeronautical pavements,” says Casimir

Bognacki, P.E., chief of materials engineering

for the Port Authority. “Our aeronautical con-

crete pavement specification holds the concrete

industry to a higher standard than national

specifications without increasing overall cost.

The Port Authority specification requires larger

stone and more stone in the concrete mix, but

less cementitious material.”

The Port Authority’s specifications produce a

“greener” concrete and reduce the potential for the

concrete to crack, Bognacki says. “This allows us

to construct our pavements with a joint spacing of

25 feet, compared to the national standard of 20

feet.The flexural strength of our concrete is about

1000 psi versus the national standard of 700 psi.”

“Quality assurance testing on the concrete mix

submitted and during production also goes

beyond national standards and most impor-

tantly, we do not accept concrete with any crack,”

says Bognacki. Concrete with cracks before the

runway is opened to traffic is removed by the

contractors at their cost, he adds. “We expect

our aeronautical concrete pavements to provide

good service for well over 50 years.”

Project Challenges

One of the challenges faced with the 4L-22R

runway project was the runway’s intersection

with other runways and the need to leave two

taxiways open for airplanes to access the termi-

nal, saysThomas Amoia, P.E., program director,

World Trade Center Construction, for the Port

Authority. Not only did this require setting con-

struction schedules that limited the times work

was performed at those intersections, but it also

required a plan to limit the need for construction

traffic to cross runways or taxiways.

“We required the contractor to erect and use

two concrete plants on the site—in locations

that would feed different parts of the project

to minimize construction traffic,” says Amoia.

“We did work off hours to minimize closures and

would capture some of the next stage when we

were at locations that required closure to access

the site.” The combination of flexible project

scheduling and two operating batch plants on

site enabled the Port Authority to deliver a better

product, he adds.

continues on page 12 »

» continued