Table of Contents Table of Contents
Previous Page  5 / 20 Next Page
Information
Show Menu
Previous Page 5 / 20 Next Page
Page Background www.acpa.org

Quarter 1, 2017

7

K A N S A S D E S I G N - B U I L D

Gateway Interchange Constructors (GIC), a joint

venture team of Clarkson Construction and

Kiewit Construction, worked with design teams

HDR and GBA to complete the project.

One of the most significant challenges for the

contractor was the requirement to keep a mini-

mum of three lanes open at all times and limit

closures of ramps and side streets, says Bryan

Wilkerson, senior project manager at Clarkson

Construction. “There was a lot of phase work in

the project. For each phase, we had to make sure

that we had enough room to work while paving,

and we had to make sure we paved far enough

to be able to switch traffic back onto the road to

allow construction in other lanes.”

Paving strip maps—diagrams that broke

down each phase of the project by laying out

all paving work with lane widths and joint

placements—were created. “The maps made it

clear what lane line and what joint the crew had

to reach for each phase, and they included the

type of pavement thickness, reinforced or non-

reinforced,” Wilkerson explains. This approach

kept everyone on track so that each day the crews

knew how far they needed to remove pavement,

how wide the grade needed to be, where base

rock was placed, where joints were located and

how far the barriers needed to go. “The paving

strip maps were the only way to make sure that

the different crews—grading, piping, base and

concrete—stayed on target.”

Lessons learned

Because this was a large, complicated project as

well as the first major design-build by KDOT,

there were opportunities to make notes to im-

prove the next design-build project.

One way to improve would be to award the proj-

ect at a time of year that gives the construction

team time to prepare, suggests Brand. With the

contract awarded in January, the contractors

had just a couple of months to prepare for a very

fast-paced construction schedule.

“If we awarded the contract in the fall, the contrac-

tor could take advantage of winter downtime to

plan and handle pre-construction activities as

the design was developed,” says Gripka.

Effective communication—on the jobsite as well

as with the general public—was a key to the

project’s success.

Because construction of a design-build project

begins when the design is 30 to 40 percent com-

plete, it is critical tomake sure all field personnel

have access to the most up-to-date plans.

“We used all electronic plans that were updated

and uploaded in real time,” says Wilkerson. All

supervisors used an iPad to access the PlanGrid,

amobile-based construction app that gives access

to all current documents. All crews—operated

by GIC or subcontractors—were required to use

the system, with GIC providing iPads to some

of the subcontractors.

“If field design changes are made or new plans

added, supervisors are notified that some pages

have been changed when they logon to the app,”

explainsWilkerson. A simple update that takes 30

seconds ensures the supervisor is working from

the current plan. The platform included plans,

shop drawings, material certifications and the

paving strip maps, he adds. “There were more

than 5,000 plan pages on this project, so the

electronic approach was the only way to guar-

antee that everyone had the same information.”

KDOT’s communications team also kept the

public up to date on closures, progress and ac-

tivities associated with the project. Ongoing

updates were shared through the website, Twitter,

Facebook, text messages, and electronic newslet-

ters. “It was important that we kept everyone up-

dated—especially emergency personnel—when

we closed roads for construction or to remove

bridges,” says Gripka. “Overall, we received very

few complaints for a project this size because

people had access to the information.”

The success of this project does prove that design-

build is a good option for highway construction,

says Gripka. “This was a very large project, but I

also believe design-build is an effective approach

for some medium to large projects as well.”