b o w m a n a i r p o r t

Pr ject

Snapshot

Bowman Reg i onal a i rport

»

»

5,700-foot long runway—longest

general aviation runway in North Dakota

»

»

Project started May 1, 2014

»

»

38 inches of rain—three times

normal—during construction period

»

»

Project completed September 29,

2015—two days earlier than scheduled

»

»

Total cost: $6,606,440

»

»

94,227 square yards of concrete

used in total project