Table of Contents Table of Contents
Previous Page  8 / 24 Next Page
Information
Show Menu
Previous Page 8 / 24 Next Page
Page Background

Concrete Pavement Progress

www.acpa.org

6

continues on page 8 »

A 5,700-foot by 75-foot runway,

taxiways,

hangars, aprons and an access road at the new

Bowman Regional Airport in North Dakota is

all concrete after the Federal Aviation Authority

(FAA) and the North Dakota Aeronautics

Commission allowed for a 12 percent Life-Cycle

Cost Allowance in the bid process.

In the end, a 6-inch-thick concrete bid was only

6.8 percent higher than the asphalt bid alterna-

tive, which consisted of 4 inches of asphalt and

2 inches of additional base course.

“Concrete is not an option for many general avia-

tion airports due to the thinner pavement sec-

tions, even with Life-Cycle Cost Analysis and

alternate bid processes,” said Gary Brennan, PE,

senior project engineer with Brosz Engineering.

“We had a rare opportunity with this project

because the cost of oil had risen, which closed

the gap between the cost of asphalt and concrete.”

There were several welcome advantages to build-

ing a new facility versus renovating or expanding

an existing airport, explained Brennan. “The

overall project had to be bid inmultiple contracts

to fit the available budget, which allowed for the

surfacing improvements to be bid separately,”

he said. “This made it easier to complete the

surfacing improvements in a single construc-

tion season.”

Because the subgrade and base work was com-

pleted in the construction season prior to paving,

the subgrade went through a winter exposure to

deep frost. “This exposure allowed us to discover

frost impacted soils and repair them prior to

paving operations,” explained Brennan.

While working at a new airport does not carry

the same security concerns as an operating air-

port, Brennan noted that he would recommend

more access control. “A security fence around

Concrete Selected for

General Aviation Project af ter

Life-Cycle Cost Analysis

By Sheryl S. Jackson

the perimeter would have been cost prohibi-

tive during construction, but some temporary

access control would have limited the number

of ‘windshield inspections’ we experienced as

people drove by,” he said. “We had no major

problems, but everyone had to be cautious of

cars and people who came onto the site to just

have a look at what we were doing.”

One of the key challenges of the project was re-

lated to the FAA specifications that require alkali-

silica reactivity (ASR) testing of the aggregates

b o w m a n a i r p o r t