Table of Contents Table of Contents
Previous Page  7 / 22 Next Page
Information
Show Menu
Previous Page 7 / 22 Next Page
Page Background www.acpa.org

Quarter 4, 2016

7

K S T r a f f i c w a y

Lengthy planning, design,

and construction

timelines for major roadway projects are not

uncommon, but when wetlands are involved,

the timeline can grow even longer.

Construction of 6.3mile, four-lane, $130million

project trafficway in Lawrence, Kans., required

the contractor to construct approximately 300

acres of manmade wetlands to replace 56 acres

of wetlands needed for the road and to serve as

a buffer to existing wetlands and habitat.

Although construction began in November

2013 and was completed in the fall of 2016, the

preliminary design for the project was done 25

years ago, said Michelle Anschutz, P.E., field

engineering administrator for the Kansas De-

partment of Transportation (KDOT). The first

design for a perimeter road to relieve traffic in

the City of Lawrence was completed in 1991,

but construction of the eastern segment was

delayed to resolve issues with wetlands man-

aged by Baker University and Haskell Indian

Nations University.

The Kansas DOT, Missouri/Kansas Chapter-

ACPA, and Emery Sapp and Sons (ESS), anACPA

member company, employed different technolo-

gies and techniques to minimize disruption to

existing wetlands.

“Geotextile fabric around clean rock did add

to the cost of the project, but it was important

that the road not affect water flow and drainage,”

Anschutz said.The use of concrete pavement was

another way to ensure minimal impact on the

wetlands, she added. “We won’t have to recon-

struct or conduct major repairs for a long time.”

Delivering the granular material for the sub-

grade required careful planning in order to

minimize the pounds per square inch (PSI)

exerted as the road was constructed, according

to Chip Jones, branch manager of the heavy

highway operations branch of ESS. “We used

crane mats to distribute the weight of small

tractor trailers that would dump, and then small

bulldozers pushed the material forward,” he says.

“Procurement of the rock materials as well as

finding and scheduling the number of trucks

required was a full-time job,” he said.

“We also used Cat 740s with scraper pans for

grading because we were able tomove dirt faster,”

Jones said. “This was helpful because we’ve had

a lot of rain in the past 1.5 years, and we were

able to stay ahead of schedule.”

A construction technique unique to working in

wetlands was the use of machetes to hand clear

the area. “One lesson we learned was not to have

the subcontractor’s crews work too far ahead of

the grading operation,” Jones said. “There were a

lot of cattails in the area, which grows fast, and if

the crew did not stay just in front of the grading

operations, they’d have to come back to clear

an area they cleared a couple of weeks before.”

Another technique used in the South Lawrence

project that is not new to road construction but

was new to KDOT was stringless paving, Jones

said. There was some apprehension within the

DOT because inspectors don’t have the typical

reference points they use when paving pins and

strings are used to guide the paver. “We devel-

oped a way to share the data with them so they

could verify slope and elevation throughout the

project, he adds.

“We recommended stringless technology because

it provides a better product—a smoother ride,”

Jones said. “Not only did we eliminate the risk

of human error when setting strings, but we also

used theGOMACOSmoothness Indicator

®

(GSI),

High- and Low-Tech Strategies

Help Protect Wetlands

By Sheryl S. Jackson

continues »