Table of Contents Table of Contents
Previous Page  16 / 22 Next Page
Information
Show Menu
Previous Page 16 / 22 Next Page
Page Background

Concrete Pavement Progress

www.acpa.org

16

“The contractual grinding specs were to meet a Half-car

Roughness Index (HRI) of less than or equal to 150 in. per

mile at a maximum grind depth of 0.5 in.,” he explains.

“If the concrete pavement smoothness couldn’t meet this

specification, then the contractor had to meet a HRI per-

cent improvement of 50 percent or greater per segment per

travel lane. If the pavement already had anHRI of less than

or equal to 150 inches per mile then the contractor had to

meet an HRI of less than or equal to 80 inches per mile

without exceeding the one-half inchmaximumgrind depth.”

To determine the extent and depth of grinding, the con-

tractor, Multiple Concrete Enterprises (MCE), conducted

a preliminary profile with a high speed profiler to calculate

the roughness index, explains JimMcGee, general manager

of MCE. “If the road segment was outside the specifications,

that segment was repaired.”

In addition to the grinding, some panels had to be replaced

or repaired. Some of the original 35-year-old panels also

required joint resealing.

As most of the roads in Highlands Ranch are residential,

traffic and noise concerns had to be addressed. Lessons

learned in the first year of the four-year project were applied

to subsequent years to address resident concerns, including:

» Project phasing

Lane closures were required for the duration of the

project. In the first phase, closures were extended to

allow for three to four weeks of work and remained in

place during construction. This generated many traffic

flow issues through the length of the work zone. Traffic

backups were resolved in the second phase with lane

closures that reflected one to two days of work and daily

removal of traffic control devices.

» continued from page 15

h i g h l a n d s r a n c h , c o